(as of June 1, 2006)
476,555 Building Gross Square Ft
Six Floors
All Clinical Space
Children's Hospital
Maternity Center
Adult Critical Care Center
Emergency Center
Private Patient Rooms
New Entrance
Enhanced Security
|
|
Project Cost: $193.6 million, $233.8 million
|
|
|
Building Costs and Site Preparation
|
$142.2
|
|
|
|
Architect and Engineering
|
10.5
|
|
|
|
Contingency, Admin Fees (includes central plant, Jacobs, PLA, Legal, MOUs)
|
20.4
|
|
|
|
Equipment
|
19.4
|
|
|
|
Parking
|
1.0
|
|
|
|
Project Costs
|
$193.6
|
million
|
|
|
|
Capitalized Interest, Negative Arbitrage, Insurance
|
23.5
|
|
|
|
Debt Reserve Fund, FHA Assignment
|
11.5
|
|
|
|
Issuance, Underwriting
|
5.5
|
|
|
|
Issuance Costs
|
$40.3
|
million
|
|
|
|
Total Project Costs (excluding debt service)
|
$233.8
|
million
|
|
|
Emergency Center
|
|
|
Adult Unit, 40 beds
|
|
|
Metabolic Unit, 6 beds
|
|
|
Trauma Unit, 6 beds
|
|
|
Observation Unit, 14 beds
|
|
|
Pediatric Unit, 11 beds
|
|
|
Imaging Center
|
|
|
|
1 MRI
2 CT's
2 RF Rooms
-
|
|
Adult Critical Care
|
|
|
Burn/Trauma/Surgical Intensive Care, 24 beds
|
|
|
Medical Intensive Care Unit, 24 beds
|
|
|
Neurosciences Intensive Care Unit, 24 beds
|
|
|
Maternity Center
|
|
|
Labor & Delivery, 15 rooms (12 LDRs, 3 ORs)
|
|
|
High Risk Antepartum, 15 rooms
|
|
|
OB Triage, 6 suites
|
|
|
Postpartum, 24 rooms
|
|
|
Newborn Nursery, 39 bassinets
|
|
|
Children's Hospital
|
|
|
Pediatric Intensive Care Unit, 20 beds
|
|
|
Pediatric Acute Unit, 34 beds
|
|
|
Pediatric Oncology Unit, 20 beds
|
|
|
Pediatric Surgery Suite, 4 OR suites
|
|
|
Carrie Tingley Hospital, 15 beds, providing coordinated healthcare
to children and adolescents with complex
musculoskeletal and orthopedic conditions, rehabilitation
needs, developmental issues, and long-term physical
disabilities.
|
|
|
Neonatal Unit, 52 beds
|
|
|
Child Life Center
|
|
|
Tentative Schedule:
|
|
August 19, 2004
|
County Commission Approval
|
|
August 20, 2004
|
Commission on Higher Education Approval
|
|
September 14, 2004
|
State Board of Finance Approval
|
|
September, 2004
|
Bond Issue
|
|
October 2004
|
Award Contract--Groundbreaking
|
|
October 2004
|
FHA Loan Closing
|
|
March 2007
|
Occupy West Wing
|
|
November 2007
|
Final Completion
|
|
|
|
|
|